Apart from the devastating impact that COVID-19 continues to unleash on human beings and countries worldwide, its outreach has also reached commerce and business. COVID-19 has resulted in lockdowns or restricted movements in countries.
Consequently, businesses have been impacted and so have operations and consequently contracts and obligations under contracts are being revisited to assess these impacts. The term that has assumed relevance in contractual context today for businesses today and heard most often is “force majeure” and how will this term be construed in a contract in the background of COVID-19.
We have, through these questions and answers endeavored to demystify the concept of “force majeure” and “frustration of a contract”, the importance of the same in businesses, the difference between the two, key aspects that one may wish to keep in mind while drafting a force majeure clause and the repercussions of COVID-19 on contracts in India in light of “force majeure” and “frustration of a contract”.
Q1. What do you mean by “force majeure”?
The term ‘force majeure’ has been defined in Black’s Law Dictionary, as ‘an event or effect that can be neither anticipated nor controlled. It is a contractual provision allocating the risk of loss if performance becomes impossible or impracticable, especially as a result of an event that the parties could not have anticipated or controlled.’ While force majeure has neither been defined nor specifically dealt with, in Indian statutes, some reference can be found in Section 32 of the Indian Contract Act, 1872 (the “Contract Act”) envisages that if a contract is contingent on the happening of an event which event becomes impossible, then the contract becomes void.
From a contractual perspective, a force majeure clause provides temporary reprieve to a party from performing its obligations under a contract upon occurrence of a force majeure event.
A force majeure clause typically spells out specific circumstances or events, which would qualify as force majeure events, conditions which would have be fulfilled for such force majeure clause to apply to the contract and the consequences of occurrence of such force majeure event. As such, for a force majeure clause to become applicable (should any force majeure event occur), the occurrence of such events should be beyond control of the parties and the parties will be required to demonstrate that they have made attempts to mitigate the impact of such force majeure event. If an event or circumstance comes within the ambit of a force majeure event and fulfils the conditions for applicability of the clause then the consequence would be that parties would be relieved from performing their respective obligations to be undertaken by them under the contract during the period that such force majeure events continue.
Further consequential liabilities, depending on the language of the clause, the parties maybe required to issue a notice formally intimating the other party of the occurrence of such event and invocation of the force majeure clause. Some contracts also contain a provision that if such force majeure event continues for a prolonged time period, the parties may be permitted to terminate the contract.
Q2. What would force majeure clauses typically include and what happens if, a contract does not include a force majeure clause?
A force majeure clause in a contract would typically include an exhaustive list of events such as acts of God, war, terrorism, earthquakes, hurricanes, acts of government, explosions, fire, plagues or epidemics or a non- exhaustive list wherein the parties simply narrate what generally constitute force majeure events and thereafter add “and such other acts or events that are beyond the control of parties”. As discussed above, it would also include conditions which would have be fulfilled for such force majeure clause to apply to the contract and the consequences of occurrence of such force majeure event. Consequences would include the suspension of obligations of the parties upon occurrence of a force majeure event.
If a contract does not include a force majeure clause, the parties would have to ascertain in light factors such as the nature of the contract, the nature of event and so forth, as to whether Section 56 of the Contract Act (which deals with agreements between the parties to do an impossible act) and which has been briefly discussed below, can be applied to such contract so as to discharge the parties from their contractual obligations.